Microsoft Project Step by Step-Chapter2 PDF | PDF | Hyperlink | Top Down And Bottom Up Design

by

in

Looking for:

Tutorial Ms Project | PDF | Project Management | Microsoft Windows

Click here to Download

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

More broadly, what are called tasks in Project are sometimes also called activities or work packages. As you might expect, Project focuses primarily on time. Remember that Project is not just merely a static repository of your schedule information or a Gantt chart drawing tool; it is an active scheduling engine.

Before a major change to the scope of a project is allowed, it must be evaluated and approved by the people managing and implementing the project.

Even though this is an important project manage- ment activity, it is not something done directly within Project.

In this exercise, you create a new project plan, set its start date, and save it. Click the File tab. Project displays the Backstage view. Click the New tab. Project displays your options for creating a new project plan. For this exercise, you will create a new blank project plan. Under Available Templates, make sure that Blank project is selected, and then click the Create button on the right side of the Backstage view. Notice the thin orange vertical line in the chart portion of the Gantt Chart view.

On the Project tab, in the Properties group, click Project Information. For more information about Project Server, see Appendix C. Tip In the calendar, you can navigate to any month and then click the date you want, or click Today to quickly choose the current date.

Project Standard users do not see this portion of the dialog box. Click OK to accept this start date and close the Project Information dialog box. On the File tab, click Save. Because this project plan has not been previously saved, the Save As dialog box appears. Entering Task Names In the File name box, type Simple Tasks. Click Save to close the Save As dialog box. Here are some guidelines for creating good task names:.

Click the cell directly below the Task Name column heading. Your screen should look similar to the following illustration. The indicators in this column tell you whether a task is manually or automatically scheduled. Product scope describes the quality, features, and func- tions of the deliverable of the project.

Project scope, on the other hand, describes the work required to deliver such a product or service. In our scenario, the project scope includes detailed tasks relating to generating publicity and advance reviews for the book. Entering Durations In this section, you begin to work with task durations—the amount of time you expect it will take to complete the task. If you estimate that a task will take 16 hours of working time, you could enter its duration as 2d, to schedule work over two eight-hour workdays.

With manually scheduled tasks, you can enter regular duration values using the microsoft project 2010 step by step tutorial pdf free viations shown previously; for example, 3d for three days.

Entering Durations Project uses standard values for minutes and hours for durations: 1 minute equals 60 seconds, and 1 hour equals 60 minutes. With a setting of 8 hours per day, entering a two-day task duration 2d is the same as entering 16 hours 16h. With a setting of 40 hours per week, entering a three-week task duration 3w is the same as entering hours h. Click the cell below the Duration column heading for task 1, Assign launch team members. Enter the following durations or text phrases for the following tasks:.

Project calculates the duration as seven days. Project also draws the Gantt bar for the task to span these working days plus http://replace.me/9516.txt nonworking days the weekend between them, as shown here. You should consider two источник статьи rules when estimating task durations:. In general, you should measure task dura- tions at the lowest level of detail or control that is important to you, but no lower.

For the projects microsoft project 2010 step by step tutorial pdf free work on in this microsoft project 2010 step by step tutorial pdf free, the durations are usually supplied for you. For your projects, you will often have to estimate task durations. Good sources of task duration estimates include:. Because inaccurate task duration estimates are a ma- jor source of risk in any project, making good estimates is well worth the effort expended. Click the name of task 3, Public Launch Phase.

On the Task tab, in the Insert group, click Milestone. Project inserts a row for a new task and renumbers the subsequent tasks. On the Gantt chart, the milestone appears as a diamond. Tip You can mark a task of any duration as a milestone. For example, it is common to divide book publishing proj- ects into Editorial, Design, and Production phases. You create phases by indenting and outdenting tasks.

In Project, phases are represented by summary tasks, and the tasks indented below the summary task are called subtasks. When a summary task is manually scheduled, its duration will be calculated based on its subtasks, just like the microsoft project 2010 step by step tutorial pdf free of an automatically scheduled summary task.

However, you can edit the duration of a manually scheduled task and Project will keep track of both the manual duration that you entered and the microsoft project 2010 step by step tutorial pdf free duration.

Select the names of tasks 5 through 7. On the Microsoft project 2010 step by step tutorial pdf free tab, in the Schedule group, click Indent Task. Indent Download microsoft office 2010 64 bit free full version free download Project promotes task 4 to a summary task.

Or you can think of it as Project demoting tasks 5 through 7 to subtasks; either way, the project plan now includes a summary task. Summary task Summary task bar in the Gantt chart. Select the name of task 1, Assign launch team members. On the Task tab, in the Insert group, click Summary.

Project inserted a row for a new task, indented the task directly below it, and renumbered the subsequent tasks. With the name of the new summary task selected, type Planning Phase and press Enter. Select the names of tasks 3 and 4. You will indent these tasks under the summary task 1. Likewise, any task can be a successor to one or more predecessor tasks. Although this might sound complicated, tasks can have one of only four types of task relationships. Tip You can adjust the schedule relationship between predecessor and successor tasks microsoft project 2010 step by step tutorial pdf free lead and lag time.

For example, you can change task durations or add or remove tasks from a chain of linked tasks, and Project will reschedule tasks accordingly. Linking Tasks You create task relationships by creating links between tasks. Select the names of tasks 2 and 3. On the Task tab, in the Schedule group, click Link Tasks. Link Capture one 12 free The change highlighting indicates The link line values that are affected after you indicates a task make a change in a project.

Tip To unlink tasks, select the tasks you want to unlink, and then click Unlink Tasks in the Schedule group on the Task tab. Select the name of task 4, Planning complete! On the Task tab, in the Properties group, click Information. Click the Predecessors tab. Click the empty cell below the Task Name column heading, and then click the down arrow that appears. On the Task Name list, click Design and order marketing material.

Select the names of tasks 6 through 8. In the chart portion of the Gantt Chart view, point the mouse pointer at the Gantt bar for task 1, Planning Phase, and then click and drag to the Gantt bar for task 5, Public Launch Phase.

When the mouse pointer is over task 5, note the link line ссылка на страницу icon that appear. Release the mouse pointer. This tooltip can help you The mouse pointer changes to link tasks using the mouse. The red squiggly line indicates a potential scheduling problem. Select the name of task 4. On the Task tab, in the Schedule group, click Respect Links.

Project reschedules task 4 to start following the completion of its predecessor, task 3. You might have noticed that the start of the Public Launch Phase summary task does not respect its link to its predecessor, the Microsoft project 2010 step by step tutorial pdf free Phase summary task. Switching Task Scheduling from Manual to Automatic In this exercise, you convert some tasks and then the entire project plan to automatic scheduling. Select the names of tasks 2 through 4.

On the Task tab, in the Tasks group, click Auto Schedule. Project switches these tasks to be automatically scheduled. Indicators in the Task Mode column The formatting of automatically tell you that these tasks are now scheduled task bars is microsoft project 2010 step by step tutorial pdf free automatically scheduled.

 
 

 

Microsoft Project Advanced – PDF Free Download

 
Custom Fields This allows you to add custom fields to the task. Start your project Open Project and More information. Deadline dates can affect the total slack on tasks. This information can then be compared against the Plan and the differences highlighted.

 
 

Microsoft Project Step by Step – PDF Drive

 
 
Aug 07,  · idk if there’s already a mod for it but it would be cool if this mod added a on-screen keyboard in game so we can type on chat, change world name or . Aug 03,  · Free video calls with one click, no sign ups, no downloads, no passwords. With Meet Now in the Windows 10 taskbar, Outlook, and more, Enjoy our latest features on the new Skype for Web using the most current versions of Microsoft Edge or Google Chrome. For any academic help you need, feel free to talk to our team for assistance and you will never regret your decision to work with us. We are reliable and established You can entrust all your academic work to course help online for original and high quality papers submitted on time.


Comments

Leave a Reply

Your email address will not be published. Required fields are marked *